Construction Project Update Week of 10/13/2025

Post Date:10/13/2025 10:55 AM
The City of Findlay is performing numerous construction projects throughout the city. The status of some of the projects is weather and contractor schedule permitting. Listed below are some of the projects and the restrictions that result from the ongoing projects. These restrictions are in effect from October 13, 2025, until further notice.

KIRK DRIVE – Western Avenue to Spring Lake Drive West – Kirk Drive will be closed to all traffic in sections from Western Avenue to Spring Lake Drive West for a sanitary sewer project.

PENROSE DRIVE – Western Avenue to Dead End – Penrose Drive will be closed to all traffic in sections from Western Avenue to Dead End for a sanitary sewer project.

KENNISON DRIVE – Penrose Drive to Spring Lake Drive West – Kennison Drive will be closed to all traffic in sections from Penrose Drive to Spring Lake Drive West for a sanitary sewer project.

SPRING LAKE DRIVE WEST – TR 80 to Dead End – Spring Lake Drive West will be closed to all traffic in sections from TR 80 to Dead End for a sanitary sewer project.

HURD AVENUE – Sandusky Street to Putnam Street – Hurd Avenue will be closed to all traffic from Sandusky Street to Putnam Street for sanitary sewer replacement.

SHERRY STREET – Sixth Street to Pearl Street – Sherry Street will be closed to all traffic from Sixth Street to Pearl Street for a sanitary sewer project.

SR 568 – Trail 237 to TR 242 – SR 568 will be maintained with portable traffic lights from Trail 237 to TR 242 for the installation of Greenway Trail Phase 3.

The Engineering Department will release updates on information and schedules when it becomes available. Please do not hesitate to contact us if you have any questions about any of these projects at 419-424-7121.

Return to full list >>