Construction Project Update Week of 9/1/2025

Post Date:09/02/2025 10:08 AM
The City of Findlay is performing numerous construction projects throughout the city. The status of some of the projects is weather and contractor schedule permitting. Listed below are some of the projects and the restrictions that result from the ongoing projects. These restrictions are in effect from September 1, 2025, until further notice.

TWP RD 77 (WESTERN AVENUE) – TWP RD 80 to Trail 81 – Twp. Road 77 (Western Avenue) will be closed to through traffic from Twp. Rd. 80 to Trail 81 for a sanitary sewer project.

MORRICAL BLVD – Logan Avenue to Bliss Avenue – Morrical Blvd will be closed to through traffic from Logan Avenue to the end of Bliss Avenue for waterline installation.

BROOKVIEW COURT – Brookside Drive to Cul-de-sac – Brookview Court will be closed to through traffic to from Brookside Drive to the cul-de-sac for milling and paving.

FOXFIRE LANE (S.) – Fox Run Road to Foxtail Drive – Foxfire Lane will be closed to through traffic to from Fox Run Road to the cul-de-sac for milling and paving.

CARNAHAN AVENUE – Railroad to Tiffin Avenue – Carnahan Avenue will be closed to through traffic from the Railroad to Tiffin Avenue for milling and paving.

BROAD AVENUE – Trenton Avenue to Melrose Avenue – Broad Avenue will be reduced to one lane in each direction from Trenton Avenue to Melrose Avenue for concrete repairs.

STATE ROUTE 568 – Trail 237 to TR 242 – SR 568 will be maintained with portable traffic lights from Trail 237 to TR 242 for the installation of Greenway Trail Phase 3.

Motorists are advised to avoid these areas if possible. Short delays are expected in these areas over the next week.

The Engineering Department will release updates on information and schedules when it becomes available. Please do not hesitate to contact us if you have any questions about any of these projects at 419-424-7121.